S01-04-01-01 DESIGN DATA CLEARANCES LV OVERHEAD SERVICE LINES 5 04/2019
S01-04-01-02 CLEARANCES LV OVERHEAD LINES 10 04/2019
S01-04-01-03 DESIGN DATA CLEARANCES HV OVERHEAD LINES UP TO 132KV 14 02/2019
S01-04-01-04 DESIGN DATA ROUTE CLEARANCE DISTRIBUTION AND TRANSMISSION LINES 4 04/2019
S01-04-01-05 DESIGN DATA LV SERVICES TWISTED CONDUCTOR GENERAL ARRANGEMENT 6 05/2019
S01-04-01-06 DESIGN DATA CONDUCTOR APPLICATION CHART FOR PAWA STANDARD OVERHEAD ALUMINIUM CONDUCTORS 7 04/2019
S01-04-01-07 DESIGN DATA CONDUCTOR URBAN AND RURAL POWER TRANSFER CAPACITY 7 04/2019
S01-04-01-08 OVERHEAD CONDUCTORS ELECTRICAL & PHYSICAL CHARACTERISTICS 4 04/2019
S01-04-01-09 CURRENT CARRYING CAPACITIES OF PAWA STANDARD OVERHEAD ALUMINIUM CONDUCTORS 5 04/2019
S01-04-01-10 CHART WAVE SAGGING 1 04/2019
S01-04-01-11 CHART WAVE SAGGING & SAG CORRECTION 1 04/2019
S01-04-01-12 CHART WAVE SAGGING & SAG CORRECTION (EXAMPLE ONLY) 1 04/2019
S01-04-01-13 SAG CALCULATION UNEVENLY SUPPORTED SPANS 2 04/2019
S01-04-01-14 CHART BASIC SPAN 1 04/2019
S01-04-01-17 GUY SELECTION NOMOGRAM 4 04/2019
S01-04-01-18 WORKED EXAMPLE DEVIATION GUY SELECTION 2 04/2019
S01-04-01-21 BOLTED POLES, CROSSARM AND FOUNDATION STRENGTHS 5 04/2019
S01-04-01-23 MINIMUM CLEARANCES FOR MINOR AIRSTRIP 2 04/2019
S01-04-02-01 FUSE CHARTS MAJOR CENTRES 11KV & 22KV EDO/LV FUSE 5 05/2019
S01-04-02-02 MINOR CENTRES 11KV EDO/LV FUSE 4 05/2019
S01-04-02-03 22KV SECTIONALISER SETTINGS 2 04/2019
S01-04-03-01 NAMING CONVENTION FOR POWER NETWORKS ASSETS 1 04/2019
S01-04-04-01 POLE INSTALLATION PROCEDURE - CIVIL WORKS 2 11/2019