The Undergrounding Power Project

The Undergrounding Power Project has now been completed in Nightcliff with around 700 properties now having underground power. Work to underground the power supply to around 675 properties in Rapid Creek commenced in October 2006 with the first 343 properties due to be completed by mid-2008. The remaining properties are due to be completed by late 2008. Design work has commenced on Millner, which is the next suburb programmed for undergrounding power.

Conduits in trench

Works program

Stage A Package Areas A2-A5, comprising 329 properties, are now being supplied with underground power. Work on the second half of Nightcliff (known as Package Areas A6-A10) is expected to be completed by end 2006. Each package area comprises between 50 and 100 homes.

Community consultation is crucial to the success of this project, as was experienced during the pilot project carried out in 1997/98. The project team has adopted a direct personal consultation approach with residents before, during, and on completion of the project. This is being done through personal letters, newspaper advertisements and a 1800 freecall number.

Step 1 of the works involves directional boring under road crossings and into properties to install conduits into which the new underground cables will be placed.

Step 2 of the works involves digging a shallow trench along the nature strip. Conduits are then laid and backfilled with cement-stabilised sand. A concrete cover is laid as protection for the cables and to serve as the footpath.

Step 3 involves installing cables into the new conduits from the pillar which are then terminated at the existing meter box/supply point at each property.

Step 4 involves changing the power supply from overhead to the new underground supply.

Media Releases
19 March 2007 Nightcliff powerlines to be demolished

The finished product - Dick Ward DriveProject Management and Community Consultation

Nilsen Electric (NT) have been engaged by Power and Water as the Managing Contractor, who are responsible for the planning and detailed design work through to construction and final handover of the assets back to Power and Water.

To date, contracts to the value of $16 million have been awarded to local Territory businesses for labour and materials associated with the project for the undergrounding of power in Nightcliff/Rapid Creek so far.

Community consultation is crucial to the success of this project, as was experienced during the pilot project carried out in 1997/98. The project team has adopted a direct personal consultation approach with residents before, during, and on completion of the project.

 

Contact Details

Residents of Nightcliff and Rapid Creek are encouraged to contact project staff to find out when their street will be undergrounded.

Telephone 1800 000 761
Email undergrounding.power@powerwater.com.au
Schedule of Works Scheduling of the works