POWER SUPPLY
AMENDMENT BULLETIN 28,
December 2008
Listed below are amended and/or new drawings that have been incorporated into this edition of the Standard Drawings.
It is important that you familiarise yourself with these drawings to ensure that you are fully aware of the latest standard materials and practices. It is the responsibility of all supervisors to ensure that all staff under their control are made aware of the implications of new or amended standard drawings.
| VOLUME 1 - Overhead Line Manual | |||
| Drawing No | Drawing Title | Amdt | Month /Year |
|
Line Hardware, Optical Fibre Composite Overhead Ground Wire |
0 |
Nov 08 | |
|
Conductor, Service, Copper, XLPE Grade X-90 |
2 |
Nov 08 | |
|
Assemblies, 22kV Wishbone Arrangement, for Universal Pole construction |
1 |
Nov 08 | |
|
Pole Structures Double pole two Single Phase Regulators, General Arrangement (3 sheets) |
4 |
Nov 08 | |
|
Cable Termination HV, Dual Overhead to Underground, 11 and 22 kV |
1 |
Nov 08 | |
|
Substations, Pole Mounted, LV Terminations, General Arramgement |
11 |
Nov 08 | |
|
Design Data, Route Clearance, Distribbution & Transmission Lines |
3 |
Nov 08 | |
|
Design Data, L.V. Seervices, Twisted conductor, General Arrangement |
4 |
Nov 08 | |
| VOLUME 2 - UNDERGROUND MANUAL | |||
| Drawing No | Drawing Title | Amdt | Month /Year |
|
Cables, Aluminium - Single Core, 0.6/1 kV, XLPE |
20 |
Nov 08 | |
|
Insulating Boot |
2 |
Dec 08 | |
|
Substations, Package, General Arrangement (5 sheets) |
21 |
Nov 08 | |
|
Substations, Indoor, Cabinet *superseded* |
2 |
Dec 08 | |
|
Sign, Warning, Underground Cables *superseded* |
2 |
Oct 08 | |
|
Sign, Sticker/Number Plate, Distribution Switchgear |
1 |
Nov 08 | |
|
Signs, Underground Danger Brand, for Concrete Pavement |
1 |
Nov 08 | |
|
Striple Fuse Pilar, Front Opening (2 sheets) |
4 |
Nov 08 | |
|
Earthing, Package Substation, Construction Details |
19 |
Nov 08 | |
|
Earthing Substation Foundation, Geneeral Arrangement *superseded* |
0 |
Dec 08 | |
|
Earthing, Kiosk Substation, Construction Details |
3 |
Sep 08 | |
|
Civil, Road Crossing and Trenching Notes, All Areas |
8 |
Nov 08 | |
|
Civil, Trenching Sectioins in Footpath Allocation, All Areas |
7 |
Dec 08 | |
|
Civil, Package Substation, Cable Entry and Foundation Details |
14 |
Oct 08 | |
|
Civil, Indoor Substation, Construction Notes |
4 |
Nov 08 | |
|
Civil, Cable Route Markers |
8 |
Nov 08 | |
|
Civil, HV Consumers, Switching Station Metering Rooms, Construction Notes |
2 |
Nov 08 | |
|
Civil, Ring Main Unit 3 Way RM6, Foundation Detail *superseded* |
2 |
Oct 08 | |
|
Civil, kiosk Substation (300-1000kVA), Cable entry and foundation Details (2 sheets) |
1 |
Nov 08 | |
|
Package Substations, High Voltage, Arrangement |
1 |
Nov 08 | |
|
Design Data, Underground Cables, Power Transfer Capacity - 433 Volts |
2 |
Nov 08 | |
|
|
|
||
| VOLUME 03 - Street Lighting Manual | |||
| Drawing No | Drawing Title | Amdt | Month /Year |
|
Column, Tapered Steel, 9.0 and 12.0 Meter, Outreach Type |
20 |
Nov 08 | |
|
Column, Tapered Steel, 6.5 Meter, Curved Outreach Type |
6 |
Nov 08 | |
|
Column, Tapered Steel, 12 Meter, Post Top Type |
6 |
Nov 08 | |
|
Control Data, Time Control Pack, Wiring Diagram & Details |
7 |
Nov 08 | |
|
|
|
||
| VOLUME 04 - Aerial Bundled Cable Manual | |||
| Drawing No | Drawing Title | Amdt | Month /Year |
| VOLUME 11 - METERING MANUAL | |||
| Drawing No | Drawing Title | Amdt | Month /Year |
| VOLUME 12 - STANDARDS BULLETIN MANUAL | |||
| Drawing No | Drawing Title | Amdt | Month /Year |
|
|
|
||